PHOTOS: Julius Berger releases fresh images on progress of 2nd Niger bridge






Julius Berger Nigeria Plc has released fresh images on the progress recorded with the ongoing construction of the 2nd Niger Bridge.
In a report which accompanied the images, the company said as of January 10, 2020, the project had reached a stage of 30.12% completion.
The project is expected to be completed by February 2022. In June, the company launched a website to “allow Nigerians track the status” of the project.
Below are the newly released pictures:
Eastern Approach – Casting station – Lifting beams completed


Amakom Bridge – Bridge deck casted and parapet wall (North) installed


CH 24+000 to 24+500 – Hyraulic dredging into alignment


Western Approach – Casting station – Segments 1 and 2 launched

Niger Bridge Axis 260 – Formwork and reinforcement (North)

Soil Improvement CH 31+750 – Laying of Geotextile upper layer

Culvert and Drains CH 29+510 – Walls and bottomslabs on going


Soil Improvement CH 32+500 – Installation of PVD

Owerri Interchange Axis 50 – Bored piling on going